AMOUNT
|
DESCRIPTION
|
COST
|
TOTAL
|
1.08
|
BRIDLE LEATHER OF YOUR CHOICE
|
10.60
|
11.45
|
2
|
5/8" SS OR SB HEEL BUCKLE OF YOUR CHOICE
|
0.79
|
1.58
|
|
MISC SUPPLIES @ 20% (THREAD-RIVETS-DYE-OIL, ETC.)
|
|
2.29
|
|
MATERIALS COST
|
|
15.32
|
|
PROFIT OR RETURN ON INVESTMENT ON MATERIALS USED
|
|
0.81
|
|
MATERIALS TOTAL COST
|
|
16.12
|
.80
|
HOURS OF LABOR NEEDED TO MANUFACTURE ITEM
{ The shop rate is the total of your hourly wage and an hourly rate to cover your overhead costs }
|
SHOP RATE TOTAL
|
MATERIALS
&
SHOP RATE
TOTAL
|
|
HOURS OF LABOR NEEDED TO MANUFACTURE ITEM AT A SHOP RATE OF $ 40.00 PER HOUR
|
32.00
|
48.12
|
|
HOURS OF LABOR NEEDED TO MANUFACTURE ITEM AT A SHOP RATE OF $ 45.00 PER HOUR
|
36.00
|
52.12
|
|
HOURS OF LABOR AT A SHOP RATE OF $ 50.00 per HOUR
NATIONAL AVERAGE HOUSEHOLD INCOME
|
40.00
|
56.12
|
|
HOURS OF LABOR NEEDED TO MANUFACTURE ITEM AT A SHOP RATE OF $ 55.00 PER HOUR
|
44.00
|
60.12
|
|
HOURS OF LABOR NEEDED TO MANUFACTURE ITEM AT A SHOP RATE OF $ 60.00 PER HOUR
|
48.00
|
64.12
|